A genetic algorithm-based optimal resource-constrained scheduling simulation model

Author

Listed:
  • Sou-Sen Leu
  • Tzung-Heng Hung

Abstract

Resources for construction activities are limited in the real construction world so that scheduling must include resource allocation. Furthermore, activity duration is uncertain due to the variation in the outside environment, such as resource availabilities, weather, space congestion, etc. A new optimal resource-constrained construction scheduling simulation model is proposed in this paper, in which the effects of both uncertain activity duration and resource constraints are taken into account. Probability distribution is used to model the uncertainties of activity duration. An optimal schedule simulation model is then established in which a genetic algorithm-based search technique is adopted to search for the probabilistic optimal project duration under resource constraints. The model can effectively provide the optimal averaged project duration, cumulative project completion probabilities and the impact of influence factors on the probabilistic resource-constrained scheduling problem.

Suggested Citation

  • Sou-Sen Leu & Tzung-Heng Hung, 2002. "A genetic algorithm-based optimal resource-constrained scheduling simulation model," Construction Management and Economics, Taylor & Francis Journals, vol. 20(2), pages 131-141.
  • Handle: RePEc:taf:conmgt:v:20:y:2002:i:2:p:131-141
    DOI: 10.1080/01446190110109148
    as

    Download full text from publisher

    File URL: http://www.tandfonline.com/doi/abs/10.1080/01446190110109148
    Download Restriction: Access to full text is restricted to subscribers.

    File URL: https://libkey.io/10.1080/01446190110109148?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Liu Shu-Shun & Kuo-Chuan Shih, 2009. "A framework of critical resource chain for project schedule analysis," Construction Management and Economics, Taylor & Francis Journals, vol. 27(9), pages 857-869.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:taf:conmgt:v:20:y:2002:i:2:p:131-141. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    We have no bibliographic references for this item. You can help adding them by using this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Chris Longhurst (email available below). General contact details of provider: http://www.tandfonline.com/RCME20 .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.