Two-machine flowshop scheduling problem with coupled-operations
Author
Abstract
Suggested Citation
DOI: 10.1007/s10479-018-2967-z
Download full text from publisher
As the access to this document is restricted, you may want to search for a different version of it.
References listed on IDEAS
- Roy D. Shapiro, 1980. "Scheduling coupled tasks," Naval Research Logistics Quarterly, John Wiley & Sons, vol. 27(3), pages 489-498, September.
- Dino Ahr & József Békési & Gábor Galambos & Marcus Oswald & Gerhard Reinelt, 2004. "An exact algorithm for scheduling identical coupled tasks," Mathematical Methods of Operations Research, Springer;Gesellschaft für Operations Research (GOR);Nederlands Genootschap voor Besliskunde (NGB), vol. 59(2), pages 193-203, June.
- S. M. Johnson, 1954. "Optimal two‐ and three‐stage production schedules with setup times included," Naval Research Logistics Quarterly, John Wiley & Sons, vol. 1(1), pages 61-68, March.
- Fondrevelle, J. & Oulamara, A. & Portmann, M.-C., 2008. "Permutation flowshop scheduling problems with time lags to minimize the weighted sum of machine completion times," International Journal of Production Economics, Elsevier, vol. 112(1), pages 168-176, March.
Citations
Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
Cited by:
- Khatami, Mostafa & Salehipour, Amir & Cheng, T.C.E., 2020. "Coupled task scheduling with exact delays: Literature review and models," European Journal of Operational Research, Elsevier, vol. 282(1), pages 19-39.
- Said Aqil & Karam Allali, 2021. "On a bi-criteria flow shop scheduling problem under constraints of blocking and sequence dependent setup time," Annals of Operations Research, Springer, vol. 296(1), pages 615-637, January.
Most related items
These are the items that most often cite the same works as this one and are cited by the same works as this one.- Khatami, Mostafa & Salehipour, Amir & Cheng, T.C.E., 2020. "Coupled task scheduling with exact delays: Literature review and models," European Journal of Operational Research, Elsevier, vol. 282(1), pages 19-39.
- Mostafa Khatami & Amir Salehipour, 2021. "Coupled task scheduling with time-dependent processing times," Journal of Scheduling, Springer, vol. 24(2), pages 223-236, April.
- Nazim Sami & Karim Amrouche & Mourad Boudhar, 2024. "New efficient algorithms for the two-machine no-wait chain-reentrant shop problem," Journal of Combinatorial Optimization, Springer, vol. 47(5), pages 1-29, July.
- Bo Chen & Xiandong Zhang, 2021. "Scheduling coupled tasks with exact delays for minimum total job completion time," Journal of Scheduling, Springer, vol. 24(2), pages 209-221, April.
- David Fischer & Péter Györgyi, 2023. "Approximation algorithms for coupled task scheduling minimizing the sum of completion times," Annals of Operations Research, Springer, vol. 328(2), pages 1387-1408, September.
- Liqi Zhang & Lingfa Lu & Shisheng Li, 2016. "New results on two-machine flow-shop scheduling with rejection," Journal of Combinatorial Optimization, Springer, vol. 31(4), pages 1493-1504, May.
- Vincent T’kindt & Federico Della Croce & Mathieu Liedloff, 2022. "Moderate exponential-time algorithms for scheduling problems," 4OR, Springer, vol. 20(4), pages 533-566, December.
- Golpîra, Hêriş, 2020. "Smart Energy-Aware Manufacturing Plant Scheduling under Uncertainty: A Risk-Based Multi-Objective Robust Optimization Approach," Energy, Elsevier, vol. 209(C).
- Alexander Grigoriev & Martijn Holthuijsen & Joris van de Klundert, 2005. "Basic scheduling problems with raw material constraints," Naval Research Logistics (NRL), John Wiley & Sons, vol. 52(6), pages 527-535, September.
- A. G. Leeftink & R. J. Boucherie & E. W. Hans & M. A. M. Verdaasdonk & I. M. H. Vliegen & P. J. Diest, 2018. "Batch scheduling in the histopathology laboratory," Flexible Services and Manufacturing Journal, Springer, vol. 30(1), pages 171-197, June.
- Yadong Wang & Baoqiang Fan & Jingang Zhai & Wei Xiong, 2019. "Two-machine flowshop scheduling in a physical examination center," Journal of Combinatorial Optimization, Springer, vol. 37(1), pages 363-374, January.
- József Békési & Gábor Galambos & Michael Jung & Marcus Oswald & Gerhard Reinelt, 2014. "A branch-and-bound algorithm for the coupled task problem," Mathematical Methods of Operations Research, Springer;Gesellschaft für Operations Research (GOR);Nederlands Genootschap voor Besliskunde (NGB), vol. 80(1), pages 47-81, August.
- Miri Gilenson & Dvir Shabtay & Liron Yedidsion & Rohit Malshe, 2021. "Scheduling in multi-scenario environment with an agreeable condition on job processing times," Annals of Operations Research, Springer, vol. 307(1), pages 153-173, December.
- Peng-Yeng Yin & Hsin-Min Chen & Yi-Lung Cheng & Ying-Chieh Wei & Ya-Lin Huang & Rong-Fuh Day, 2021. "Minimizing the Makespan in Flowshop Scheduling for Sustainable Rubber Circular Manufacturing," Sustainability, MDPI, vol. 13(5), pages 1-18, February.
- Asoo J. Vakharia & Yih‐Long Chang, 1990. "A simulated annealing approach to scheduling a manufacturing cell," Naval Research Logistics (NRL), John Wiley & Sons, vol. 37(4), pages 559-577, August.
- Yu, Tae-Sun & Han, Jun-Hee, 2021. "Scheduling proportionate flow shops with preventive machine maintenance," International Journal of Production Economics, Elsevier, vol. 231(C).
- Alfaro-Fernández, Pedro & Ruiz, Rubén & Pagnozzi, Federico & Stützle, Thomas, 2020. "Automatic Algorithm Design for Hybrid Flowshop Scheduling Problems," European Journal of Operational Research, Elsevier, vol. 282(3), pages 835-845.
- Vincent T’kindt & Karima Bouibede-Hocine & Carl Esswein, 2007. "Counting and enumeration complexity with application to multicriteria scheduling," Annals of Operations Research, Springer, vol. 153(1), pages 215-234, September.
- C.T. Ng & Mikhail Y. Kovalyov, 2004. "An FPTAS for scheduling a two‐machine flowshop with one unavailability interval," Naval Research Logistics (NRL), John Wiley & Sons, vol. 51(3), pages 307-315, April.
- Christoph Hertrich & Christian Weiß & Heiner Ackermann & Sandy Heydrich & Sven O. Krumke, 2020. "Scheduling a proportionate flow shop of batching machines," Journal of Scheduling, Springer, vol. 23(5), pages 575-593, October.
More about this item
Keywords
Flowshop; Coupled-operations; Complexity; Polynomial time algorithms;All these keywords.
Statistics
Access and download statisticsCorrections
All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:spr:annopr:v:275:y:2019:i:2:d:10.1007_s10479-018-2967-z. See general information about how to correct material in RePEc.
If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.
If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .
If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.
For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Sonal Shukla or Springer Nature Abstracting and Indexing (email available below). General contact details of provider: http://www.springer.com .
Please note that corrections may take a couple of weeks to filter through the various RePEc services.