Subjective Time Estimates in Critical Path Planning--A Preliminary Analysis

Author

Listed:
  • William R. King

    (Air Force Institute of Technology)

  • Talmadge A. Wilson

    (USAF Systems Command)

Abstract

A historical analysis of activity time estimates made by a number of contractors on a large-scale systems development project is conducted using two basic hypotheses. (1) Pre-activity time estimating accuracy improves as the beginning date of the activity approaches. (2) Time estimates made during the progress of an activity improve in relative accuracy as the completion date of the activity approaches. These hypotheses are tested and several models for adjusting time estimates on the basis of the estimator's past history are developed and tested. The results are not proposed to be definitive--but rather, preliminary ones which should serve to demonstrate the feasibility of the basic approach.

Suggested Citation

  • William R. King & Talmadge A. Wilson, 1967. "Subjective Time Estimates in Critical Path Planning--A Preliminary Analysis," Management Science, INFORMS, vol. 13(5), pages 307-320, January.
  • Handle: RePEc:inm:ormnsc:v:13:y:1967:i:5:p:307-320
    DOI: 10.1287/mnsc.13.5.307
    as

    Download full text from publisher

    File URL: http://dx.doi.org/10.1287/mnsc.13.5.307
    Download Restriction: no

    File URL: https://libkey.io/10.1287/mnsc.13.5.307?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Davies, Andrew & Manning, Stephan & Söderlund, Jonas, 2018. "When neighboring disciplines fail to learn from each other: The case of innovation and project management research," Research Policy, Elsevier, vol. 47(5), pages 965-979.
    2. Robert D. Austin, 2001. "The Effects of Time Pressure on Quality in Software Development: An Agency Model," Information Systems Research, INFORMS, vol. 12(2), pages 195-207, June.
    3. Bregman, Robert L., 2009. "A heuristic procedure for solving the dynamic probabilistic project expediting problem," European Journal of Operational Research, Elsevier, vol. 192(1), pages 125-137, January.

    More about this item

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:inm:ormnsc:v:13:y:1967:i:5:p:307-320. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    We have no bibliographic references for this item. You can help adding them by using this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Chris Asher (email available below). General contact details of provider: https://edirc.repec.org/data/inforea.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.