Multidimensional Construction Planning and Agile Organized Project Execution—The 5D-PROMPT Method

Author

Listed:
  • David Leicht

    (GITECO Research Group, University of Cantabria, 39005 Santander, Spain)

  • Daniel Castro-Fresno

    (GITECO Research Group, University of Cantabria, 39005 Santander, Spain)

  • Joaquìn Dìaz

    (Department of Information Technology in Construction, University of Applied Sciences, 35390 THM Giessen, Germany)

  • Christian Baier

    (Department of Information Technology in Construction, University of Applied Sciences, 35390 THM Giessen, Germany)

Abstract

Although tremendous technological and strategic advances have been developed and implemented in the construction sector in recent years, there is substantial room for improvement in the areas of productivity growth, project performance, and schedule reliability. Thus, the present paper seeks to discover why the currently applied scheduling tools and the latest agile-based project organization approaches have not yet achieved their full potential. A missing interlinkage between the project’s design, cost, and time aspects within the project design phase and its sparse utilization throughout project execution were indicated as the driving contributors responsible for the slow progress in development. To fundamentally change this situation, an extensive and coherent project organization solution is proposed. The key process of this solution utilizes a 5D Building Information Model comprising tight concatenations between the individual model objects and the corresponding construction cost and time effort values. The key dates of a waterfall-based construction process simulation, set during the project planning phase, provide particular information to create a structure for agile organized project execution. The implementation of information feedback loops allows target/actual comparisons and contributes to continual improvements in future planning. A comparative case study was conducted with auspicious results on improvements in the overall project performance, and schedule and cost reliability.

Suggested Citation

  • David Leicht & Daniel Castro-Fresno & Joaquìn Dìaz & Christian Baier, 2020. "Multidimensional Construction Planning and Agile Organized Project Execution—The 5D-PROMPT Method," Sustainability, MDPI, vol. 12(16), pages 1-22, August.
  • Handle: RePEc:gam:jsusta:v:12:y:2020:i:16:p:6340-:d:395515
    as

    Download full text from publisher

    File URL: https://www.mdpi.com/2071-1050/12/16/6340/pdf
    Download Restriction: no

    File URL: https://www.mdpi.com/2071-1050/12/16/6340/
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Milan Radosavljevic & Malcolm Horner, 2007. "Process planning methodology: dynamic short-term planning for off-site construction in Slovenia," Construction Management and Economics, Taylor & Francis Journals, vol. 25(2), pages 143-156.
    2. Jeffrey W. Herrmann, 2006. "A History of Production Scheduling," International Series in Operations Research & Management Science, in: Jeffrey W. Herrmann (ed.), Handbook of Production Scheduling, chapter 0, pages 1-22, Springer.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Tena Žužek & Žiga Gosar & Janez Kušar & Tomaž Berlec, 2020. "Adopting Agile Project Management Practices in Non-Software SMEs: A Case Study of a Slovenian Medium-Sized Manufacturing Company," Sustainability, MDPI, vol. 12(21), pages 1-17, November.
    2. Sunkuk Kim, 2021. "Technology and Management for Sustainable Buildings and Infrastructures," Sustainability, MDPI, vol. 13(16), pages 1-3, August.
    3. Kyunghwan Kim, 2020. "Generalized Resource-Constrained Critical Path Method to Improve Sustainability in Construction Project Scheduling," Sustainability, MDPI, vol. 12(21), pages 1-19, October.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.

      Corrections

      All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:gam:jsusta:v:12:y:2020:i:16:p:6340-:d:395515. See general information about how to correct material in RePEc.

      If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

      If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

      If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

      For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: MDPI Indexing Manager (email available below). General contact details of provider: https://www.mdpi.com .

      Please note that corrections may take a couple of weeks to filter through the various RePEc services.

      IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.