2-Level Construction Planning Model With A Local Case Study

Author

Listed:
  • ERDINC Gizem

    (University of Erciyes, Faculty of Engineering, Department of Industrial Engineering)

  • GURBUZ Feyza

    (University of Erciyes, Faculty of Engineering, Department of Industrial Engineering)

Abstract

Two basic approaches underlie construction project management practices: Critical Path Method (CPM) and Program Evaluation and Review Technique (PERT). CPM widely used in the construction industry is criticized for its lacks of planning of repetitive or linear construction projects that contain the same or similar number of units such as mass housing. In this paper, a new 2-level location-based planning model (2-LCPM) has been presented to be used in the planning of construction projects consisting of repetitive activities and which is thought to eliminate the deficiencies of the existing models. It was designed at two levels: globally and locally. It provides a schedule with minimum delay to the planner at the global level while provides resource continuity at the local level. 2-LCPM was programmed in Go language and tested with a real case study by using Postman platform and SQL database. As a result, 2-LCPM is presented a new plan with increased resource continuity which are 5.32 %, 3.645% and 2.455% respectively, besides gives the same project complete time which is 15 months.

Suggested Citation

  • ERDINC Gizem & GURBUZ Feyza, 2024. "2-Level Construction Planning Model With A Local Case Study," Revista Economica, Lucian Blaga University of Sibiu, Faculty of Economic Sciences, vol. 76(2), pages 52-59, June.
  • Handle: RePEc:blg:reveco:v:76:y:2024:i:2:p:52-59
    DOI: 10.56043/reveco-2024-0015
    as

    Download full text from publisher

    File URL: http://economice.ulbsibiu.ro/revista.economica/archive/76205erdinc&gurbuz.pdf
    Download Restriction: no

    File URL: https://libkey.io/10.56043/reveco-2024-0015?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    References listed on IDEAS

    as
    1. Olli Sepp�nen & Jake Evinger & Christopher Mouflard, 2014. "Effects of the location-based management system on production rates and productivity," Construction Management and Economics, Taylor & Francis Journals, vol. 32(6), pages 608-624, June.
    2. Marco Alvise Bragadin & Kalle Kähkönen, 2016. "Schedule health assessment of construction projects," Construction Management and Economics, Taylor & Francis Journals, vol. 34(12), pages 875-897, December.
    3. POPA Daniela, 2015. "The Knowledge Of Concept Of Project Management In Small And Medium Entreprises," Revista Economica, Lucian Blaga University of Sibiu, Faculty of Economic Sciences, vol. 67(Supplemen), pages 351-362, September.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.

      More about this item

      Keywords

      Location-Based Project Planning; Construction Project Management; Resource Continuity;
      All these keywords.

      JEL classification:

      • B41 - Schools of Economic Thought and Methodology - - Economic Methodology - - - Economic Methodology
      • C02 - Mathematical and Quantitative Methods - - General - - - Mathematical Economics
      • J22 - Labor and Demographic Economics - - Demand and Supply of Labor - - - Time Allocation and Labor Supply
      • L74 - Industrial Organization - - Industry Studies: Primary Products and Construction - - - Construction
      • M11 - Business Administration and Business Economics; Marketing; Accounting; Personnel Economics - - Business Administration - - - Production Management
      • M54 - Business Administration and Business Economics; Marketing; Accounting; Personnel Economics - - Personnel Economics - - - Labor Management
      • O21 - Economic Development, Innovation, Technological Change, and Growth - - Development Planning and Policy - - - Planning Models; Planning Policy

      Statistics

      Access and download statistics

      Corrections

      All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:blg:reveco:v:76:y:2024:i:2:p:52-59. See general information about how to correct material in RePEc.

      If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

      If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

      If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

      For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Eduard Alexandru Stoica (email available below). General contact details of provider: https://edirc.repec.org/data/feulbro.html .

      Please note that corrections may take a couple of weeks to filter through the various RePEc services.

      IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.