Fast iterative improvement methods for project scheduling under partially renewable resources

Author

Listed:
  • Schirmer, Andreas

Abstract

It is well-known that for many project scheduling problems the Space AS of active schedules contains at least one optimal solution for each feasible instance, so restricting heuristic construction methods to AS will improve algorithmic efficiency without foresaking the chance to eventually find an optimal schedule. Yet, for some problems such results are not directly applicable. We address one such problem, namely the resource-constrained project scheduling problem under partially renewable resources (RCPSP/TI). Here delaying certain activities may yield better solutions than starting each activity as soon as possible. Since AS is the smallest space guaranteed to contain optimal schedules, it would be desirable to devise methods which sample AS, or at least the next-larger Space SAS of semi-active schedules. However, no such methods are in sight because the "delay problem" of which activities should be delayed and by how many periods cannot be properly addressed during the construction process, when not all remaining resource capacities are known. Indeed, all priority rulebased construction methods for the RCPSP/TI use scheduling schemes which sample the next-larger space FS of feasible schedules. But while the delay problem withstands solution during the construction of schedules, it can be solved afterwards, suggesting the idea of fast iterative improvement algorithms which use appropriate shift operations to improve heuristically constructed feasible schedules. We develop several such approaches, using local and global shifts, and evaluate the effect of different design choices on effectiveness and efficiency of the algorithms. Computational results validate the efficacy of our approach.

Suggested Citation

  • Schirmer, Andreas, 1999. "Fast iterative improvement methods for project scheduling under partially renewable resources," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 501, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
  • Handle: RePEc:zbw:cauman:501
    as

    Download full text from publisher

    File URL: https://www.econstor.eu/bitstream/10419/147589/1/manuskript_501.pdf
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Schirmer, Andreas & Drexl, Andreas, 1997. "Allocation of partially renewable resources: Concept, models and applications," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 455, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    2. Sprecher, Arno & Kolisch, Rainer & Drexl, Andreas, 1995. "Semi-active, active, and non-delay schedules for the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 80(1), pages 94-102, January.
    3. Kolisch, Rainer, 1996. "Serial and parallel resource-constrained project scheduling methods revisited: Theory and computation," European Journal of Operational Research, Elsevier, vol. 90(2), pages 320-333, April.
    4. James E. Kelley, 1961. "Critical-Path Planning and Scheduling: Mathematical Basis," Operations Research, INFORMS, vol. 9(3), pages 296-320, June.
    5. Haase, Knut & Latteier, Jörg & Schirmer, Andreas, 1997. "Course planning at Lufthansa technical training: Constructing more profitable schedules," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 442, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    6. Schirmer, Andreas & Riesenberg, Sven, 1998. "Class-based control schemes for parameterized project scheduling heuristics," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 471, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    7. Haase, Knut & Latteier, Jorg & Schirmer, Andreas, 1998. "The course scheduling problem at Lufthansa Technical Training," European Journal of Operational Research, Elsevier, vol. 110(3), pages 441-456, November.
    8. F. Brian Talbot & James H. Patterson, 1978. "An Efficient Integer Programming Algorithm with Network Cuts for Solving Resource-Constrained Scheduling Problems," Management Science, INFORMS, vol. 24(11), pages 1163-1174, July.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Schirmer, Andreas, 1999. "Adaptive control schemes applied to project scheduling with partially renewable resources," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 520, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    2. Schirmer, Andreas & Riesenberg, Sven, 1997. "Parameterized heuristics for project scheduling: Biased random sampling methods," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 456, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    3. Kolisch, R. & Padman, R., 2001. "An integrated survey of deterministic project scheduling," Omega, Elsevier, vol. 29(3), pages 249-272, June.
    4. Schirmer, Armin, 1998. "Adaptive control schemes for parameterized heuristic scheduling," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 488, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    5. Sprecher, Arno, 1996. "Solving the RCPSP efficiently at modest memory requirements," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 425, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    6. Schirmer, Andreas, 1998. "Case-based reasoning and improved adaptive search for project scheduling," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 472, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    7. Abdollah Arasteh, 2020. "Considering Project Management Activities for Engineering Design Groups," SN Operations Research Forum, Springer, vol. 1(4), pages 1-29, December.
    8. Schirmer, Andreas & Potzhar, Kathrin, 2001. "Professional course scheduling in airline transport pilot training: A case from Lufthansa flight training," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 539, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    9. Bouleimen, K. & Lecocq, H., 2003. "A new efficient simulated annealing algorithm for the resource-constrained project scheduling problem and its multiple mode version," European Journal of Operational Research, Elsevier, vol. 149(2), pages 268-281, September.
    10. Arno Sprecher, 2000. "Scheduling Resource-Constrained Projects Competitively at Modest Memory Requirements," Management Science, INFORMS, vol. 46(5), pages 710-723, May.
    11. Sprecher, Arno, 1999. "Network decomposition techniques for resource-constrained project scheduling," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 505, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    12. Hartmann, Sönke, 1999. "Self-adapting genetic algorithms with an application to project scheduling," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 506, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    13. Raúl Mencía & Carlos Mencía, 2021. "One-Machine Scheduling with Time-Dependent Capacity via Efficient Memetic Algorithms," Mathematics, MDPI, vol. 9(23), pages 1-24, November.
    14. Hartmann, Sönke & Drexl, Andreas, 1997. "Project scheduling with multiple modes: A comparison of exact algorithms," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 430, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    15. Klein, Robert & Scholl, Armin, 1999. "Computing lower bounds by destructive improvement: An application to resource-constrained project scheduling," European Journal of Operational Research, Elsevier, vol. 112(2), pages 322-346, January.
    16. Böttcher, Jan & Drexl, Andreas & Kolisch, Rainer & Salewski, Frank, 1996. "Project scheduling under partially renewable resource constraints," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 398, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    17. Shadrokh, Shahram & Kianfar, Fereydoon, 2007. "A genetic algorithm for resource investment project scheduling problem, tardiness permitted with penalty," European Journal of Operational Research, Elsevier, vol. 181(1), pages 86-101, August.
    18. Buddhakulsomsiri, Jirachai & Kim, David S., 2006. "Properties of multi-mode resource-constrained project scheduling problems with resource vacations and activity splitting," European Journal of Operational Research, Elsevier, vol. 175(1), pages 279-295, November.
    19. Lova, Antonio & Maroto, Concepcion & Tormos, Pilar, 2000. "A multicriteria heuristic method to improve resource allocation in multiproject scheduling," European Journal of Operational Research, Elsevier, vol. 127(2), pages 408-424, December.
    20. Messelis, Tommy & De Causmaecker, Patrick, 2014. "An automatic algorithm selection approach for the multi-mode resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 233(3), pages 511-528.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:zbw:cauman:501. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: ZBW - Leibniz Information Centre for Economics (email available below). General contact details of provider: https://edirc.repec.org/data/ibkiede.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.