Project scheduling with multiple modes: A genetic algorithm

Author

Listed:
  • Hartmann, Sönke

Abstract

In this paper we consider the resource-constrained project scheduling problem with multiple execution modes for each activity and makespan minimization as objective. We present a new genetic algorithm approach to solve this problem. The genetic encoding is based on a precedence feasible sequence of activities and a mode assignment. After defining the related crossover, mutation, and selection operators, we describe a local search extension which is employed to improve the schedules found by the basic genetic algorithm. Finally, we present the results of our thorough computational study. We determine the best among several different variants of our genetic algorithm and compare it to three other heuristics that have recently been proposed in the literature. The results that have been obtained using a standard set of instances show that the new genetic algorithm outperforms the other heuristic procedures with regard to a lower average deviation from the optimal makespan.

Suggested Citation

  • Hartmann, Sönke, 1997. "Project scheduling with multiple modes: A genetic algorithm," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 435, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
  • Handle: RePEc:zbw:cauman:435
    as

    Download full text from publisher

    File URL: https://www.econstor.eu/bitstream/10419/149056/1/manuskript_435.pdf
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. F. Brian Talbot, 1982. "Resource-Constrained Project Scheduling with Time-Resource Tradeoffs: The Nonpreemptive Case," Management Science, INFORMS, vol. 28(10), pages 1197-1210, October.
    2. Hartmann, Sönke & Drexl, Andreas, 1997. "Project scheduling with multiple modes: A comparison of exact algorithms," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 430, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    3. Sprecher, Arno & Kolisch, Rainer & Drexl, Andreas, 1995. "Semi-active, active, and non-delay schedules for the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 80(1), pages 94-102, January.
    4. Rainer Kolisch & Arno Sprecher & Andreas Drexl, 1995. "Characterization and Generation of a General Class of Resource-Constrained Project Scheduling Problems," Management Science, INFORMS, vol. 41(10), pages 1693-1703, October.
    5. Sprecher, Arno & Drexl, Andreas, 1996. "Solving Multi-Mode Resource-Constrained Project Scheduling Problems by a Simple, General and Powerful Sequeacing Algorithm. Part I: Theory," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 385, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    6. Kolisch, Rainer & Sprecher, Arno, 1996. "PSPLIB - a project scheduling problem library," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 396, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    7. Slowinski, Roman & Soniewicki, Boleslaw & Weglarz, Jan, 1994. "DSS for multiobjective project scheduling," European Journal of Operational Research, Elsevier, vol. 79(2), pages 220-229, December.
    8. Sprecher, Arno & Drexl, Andreas, 1996. "Solving Multi-Mode Resource-Constrained Project Scheduling Problems by a Simple, General and Powerful Sequeacing Algorithm. Part II: Computation," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 386, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    9. Speranza, M. Grazia & Vercellis, Carlo, 1993. "Hierarchical models for multi-project planning and scheduling," European Journal of Operational Research, Elsevier, vol. 64(2), pages 312-325, January.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Mick Van Den Eeckhout & Broos Maenhout & Mario Vanhoucke, 2020. "Mode generation rules to define activity flexibility for the integrated project staffing problem with discrete time/resource trade-offs," Annals of Operations Research, Springer, vol. 292(1), pages 133-160, September.
    2. Ulusoy, Gunduz & Cebelli, Serkan, 2000. "An equitable approach to the payment scheduling problem in project management," European Journal of Operational Research, Elsevier, vol. 127(2), pages 262-278, December.
    3. Hartmann, Sönke, 1997. "A comparative genetic algorithm for resource-constraint project scheduling," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 451, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    4. Kolisch, R. & Padman, R., 2001. "An integrated survey of deterministic project scheduling," Omega, Elsevier, vol. 29(3), pages 249-272, June.
    5. Kolisch, Rainer & Padman, Rema, 1997. "An integrated survey of project scheduling," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 463, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    6. T Wauters & K Verbeeck & G Vanden Berghe & P De Causmaecker, 2011. "Learning agents for the multi-mode project scheduling problem," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 62(2), pages 281-290, February.
    7. Brucker, Peter & Drexl, Andreas & Mohring, Rolf & Neumann, Klaus & Pesch, Erwin, 1999. "Resource-constrained project scheduling: Notation, classification, models, and methods," European Journal of Operational Research, Elsevier, vol. 112(1), pages 3-41, January.
    8. Drexl, Andreas & Kolisch, Rainer & Sprecher, Arno, 1997. "Koordination und Integration im Projektmanagement - Aufgaben und Instrumente," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 443, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Hartmann, Sönke & Drexl, Andreas, 1997. "Project scheduling with multiple modes: A comparison of exact algorithms," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 430, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    2. Sprecher, Arno & Drexl, Andreas, 1998. "Multi-mode resource-constrained project scheduling by a simple, general and powerful sequencing algorithm," European Journal of Operational Research, Elsevier, vol. 107(2), pages 431-450, June.
    3. Kolisch, R. & Padman, R., 2001. "An integrated survey of deterministic project scheduling," Omega, Elsevier, vol. 29(3), pages 249-272, June.
    4. Sprecher, Arno, 1996. "Solving the RCPSP efficiently at modest memory requirements," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 425, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    5. Peteghem, Vincent Van & Vanhoucke, Mario, 2010. "A genetic algorithm for the preemptive and non-preemptive multi-mode resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 201(2), pages 409-418, March.
    6. Sprecher, Arno & Drexl, Andreas, 1996. "Solving Multi-Mode Resource-Constrained Project Scheduling Problems by a Simple, General and Powerful Sequeacing Algorithm. Part II: Computation," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 386, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    7. Sprecher, Arno & Drexl, Andreas, 1996. "Solving Multi-Mode Resource-Constrained Project Scheduling Problems by a Simple, General and Powerful Sequeacing Algorithm. Part I: Theory," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 385, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    8. Nima Zoraghi & Aria Shahsavar & Babak Abbasi & Vincent Peteghem, 2017. "Multi-mode resource-constrained project scheduling problem with material ordering under bonus–penalty policies," TOP: An Official Journal of the Spanish Society of Statistics and Operations Research, Springer;Sociedad de Estadística e Investigación Operativa, vol. 25(1), pages 49-79, April.
    9. Van Peteghem, Vincent & Vanhoucke, Mario, 2014. "An experimental investigation of metaheuristics for the multi-mode resource-constrained project scheduling problem on new dataset instances," European Journal of Operational Research, Elsevier, vol. 235(1), pages 62-72.
    10. Dayal Madhukar & Verma, Sanjay, 2015. "Multi-processor Exact Procedures for Regular Measures of the Multi-mode RCPSP," IIMA Working Papers WP2015-03-25, Indian Institute of Management Ahmedabad, Research and Publication Department.
    11. Alfredo S. Ramos & Pablo A. Miranda-Gonzalez & Samuel Nucamendi-Guillén & Elias Olivares-Benitez, 2023. "A Formulation for the Stochastic Multi-Mode Resource-Constrained Project Scheduling Problem Solved with a Multi-Start Iterated Local Search Metaheuristic," Mathematics, MDPI, vol. 11(2), pages 1-25, January.
    12. V. Van Peteghem & M. Vanhoucke, 2008. "A Genetic Algorithm for the Multi-Mode Resource-Constrained Project Scheduling Problem," Working Papers of Faculty of Economics and Business Administration, Ghent University, Belgium 08/494, Ghent University, Faculty of Economics and Business Administration.
    13. Kolisch, Rainer & Padman, Rema, 1997. "An integrated survey of project scheduling," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 463, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    14. Kolisch, Rainer & Sprecher, Arno, 1997. "PSPLIB - A project scheduling problem library : OR Software - ORSEP Operations Research Software Exchange Program," European Journal of Operational Research, Elsevier, vol. 96(1), pages 205-216, January.
    15. Hartmann, Sönke, 2011. "Project scheduling with resource capacities and requests varying with time," Working Paper Series 01/2011, Hamburg School of Business Administration (HSBA).
    16. Weglarz, Jan & Józefowska, Joanna & Mika, Marek & Waligóra, Grzegorz, 2011. "Project scheduling with finite or infinite number of activity processing modes - A survey," European Journal of Operational Research, Elsevier, vol. 208(3), pages 177-205, February.
    17. Drexl, Andreas & Kolisch, Rainer & Sprecher, Arno, 1997. "Koordination und Integration im Projektmanagement - Aufgaben und Instrumente," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 443, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    18. V. Van Peteghem & M. Vanhoucke, 2009. "An Artificial Immune System for the Multi-Mode Resource-Constrained Project Scheduling Problem," Working Papers of Faculty of Economics and Business Administration, Ghent University, Belgium 09/555, Ghent University, Faculty of Economics and Business Administration.
    19. Hartmann, Sönke & Briskorn, Dirk, 2010. "A survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 207(1), pages 1-14, November.
    20. Dayal Madhukar & Verma, Sanjay, 2014. "Breadth-first and Best-first Exact Procedures for Regular Measures of the Multi-mode RCPSP," IIMA Working Papers WP2014-10-04, Indian Institute of Management Ahmedabad, Research and Publication Department.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:zbw:cauman:435. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: ZBW - Leibniz Information Centre for Economics (email available below). General contact details of provider: https://edirc.repec.org/data/ibkiede.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.