A two-phase genetic algorithm to solve variants of the batch sequencing problem
Author
Abstract
Suggested Citation
Download full text from publisher
References listed on IDEAS
- Clyde L. Monma & Chris N. Potts, 1989. "On the Complexity of Scheduling with Batch Setup Times," Operations Research, INFORMS, vol. 37(5), pages 798-804, October.
- Dirk Cattrysse & Marc Salomon & Roelof Kuik & Luk N. Van Wassenhove, 1993. "A Dual Ascent and Column Generation Heuristic for the Discrete Lotsizing and Scheduling Problem with Setup Times," Management Science, INFORMS, vol. 39(4), pages 477-486, April.
- Fleischmann, Bernhard, 1994. "The discrete lot-sizing and scheduling problem with sequence-dependent setup costs," European Journal of Operational Research, Elsevier, vol. 75(2), pages 395-404, June.
- Marc Salomon & Leo G. Kroon & Roelof Kuik & Luk N. Van Wassenhove, 1991. "Some Extensions of the Discrete Lotsizing and Scheduling Problem," Management Science, INFORMS, vol. 37(7), pages 801-812, July.
- Jordan, Carsten & Drexl, Andreas, 1994. "Lotsizing and scheduling by batch sequencing," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 343, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- Fleischmann, Bernhard, 1990. "The discrete lot-sizing and scheduling problem," European Journal of Operational Research, Elsevier, vol. 44(3), pages 337-348, February.
Most related items
These are the items that most often cite the same works as this one and are cited by the same works as this one.- Drexl, A. & Kimms, A., 1997. "Lot sizing and scheduling -- Survey and extensions," European Journal of Operational Research, Elsevier, vol. 99(2), pages 221-235, June.
- Salomon, Marc & Solomon, Marius M. & Van Wassenhove, Luk N. & Dumas, Yvan & Dauzere-Peres, Stephane, 1997. "Solving the discrete lotsizing and scheduling problem with sequence dependent set-up costs and set-up times using the Travelling Salesman Problem with time windows," European Journal of Operational Research, Elsevier, vol. 100(3), pages 494-513, August.
- Carsten Jordan & Andreas Drexl, 1998. "Discrete Lotsizing and Scheduling by Batch Sequencing," Management Science, INFORMS, vol. 44(5), pages 698-713, May.
- Sungmin Kang & Kavindra Malik & L. Joseph Thomas, 1999. "Lotsizing and Scheduling on Parallel Machines with Sequence-Dependent Setup Costs," Management Science, INFORMS, vol. 45(2), pages 273-289, February.
- Drexl, Andreas & Haase, Knut, 1995. "Proportional lotsizing and scheduling," International Journal of Production Economics, Elsevier, vol. 40(1), pages 73-87, June.
- Kimms, Alf, 1996. "Stability measures for rolling schedules with applications to capacity expansion planning, master production scheduling, and lot sizing," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 418, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- Jans, R.F. & Degraeve, Z., 2005. "Modeling Industrial Lot Sizing Problems: A Review," ERIM Report Series Research in Management ERS-2005-049-LIS, Erasmus Research Institute of Management (ERIM), ERIM is the joint research institute of the Rotterdam School of Management, Erasmus University and the Erasmus School of Economics (ESE) at Erasmus University Rotterdam.
- Drexl, Andreas & Jordan, Carsten & Kimms, Alf, 1997. "Gruppierungs- und Reihenfolgeprobleme in der Fertigung," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 447, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- Kimms, A, 1998. "Stability Measures for Rolling Schedules with Applications to Capacity Expansion Planning, Master Production Scheduling, and Lot Sizing," Omega, Elsevier, vol. 26(3), pages 355-366, June.
- Drexl, Andreas & Haase, Knut, 1997. "Vorbeugende Instandhaltung und Eilaufträge in der Produktionsplanung," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 450, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- Jans, Raf & Degraeve, Zeger, 2007. "Meta-heuristics for dynamic lot sizing: A review and comparison of solution approaches," European Journal of Operational Research, Elsevier, vol. 177(3), pages 1855-1875, March.
- Jordan, Carsten & Drexl, Andreas, 1994. "Lotsizing and scheduling by batch sequencing," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 343, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- Bruggemann, Wolfgang & Jahnke, Hermann, 2000. "The discrete lot-sizing and scheduling problem: Complexity and modification for batch availability," European Journal of Operational Research, Elsevier, vol. 124(3), pages 511-528, August.
- Meyr, H., 2000. "Simultaneous lotsizing and scheduling by combining local search with dual reoptimization," European Journal of Operational Research, Elsevier, vol. 120(2), pages 311-326, January.
- Ozdamar, Linet & Birbil, Sevket Ilker, 1998. "Hybrid heuristics for the capacitated lot sizing and loading problem with setup times and overtime decisions," European Journal of Operational Research, Elsevier, vol. 110(3), pages 525-547, November.
- Karina Copil & Martin Wörbelauer & Herbert Meyr & Horst Tempelmeier, 2017. "Simultaneous lotsizing and scheduling problems: a classification and review of models," OR Spectrum: Quantitative Approaches in Management, Springer;Gesellschaft für Operations Research e.V., vol. 39(1), pages 1-64, January.
- Drexl, Andreas & Kimms, Alf, 1996. "Lot sizing and scheduling: Survey and extensions," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 421, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- Drexl, Andreas & Haase, Knut, 1993. "Sequential-analysis-based randomized-regret-methods for lotsizing and scheduling," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 323, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- Lee, Younsoo & Lee, Kyungsik, 2020. "Lot-sizing and scheduling in flat-panel display manufacturing process," Omega, Elsevier, vol. 93(C).
- Schirmer, Andreas, 1996. "New insights on the complexity of resource-constrained project scheduling: Two cases of multi-mode scheduling," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 391, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
Corrections
All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:zbw:cauman:363. See general information about how to correct material in RePEc.
If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.
If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .
If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.
For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: ZBW - Leibniz Information Centre for Economics (email available below). General contact details of provider: https://edirc.repec.org/data/ibkiede.html .
Please note that corrections may take a couple of weeks to filter through the various RePEc services.