Author

Listed:
  • Iimi, Atsushi
  • Benamghar, Radia

Abstract

Procurement packaging has important effects on not only the bidders'bidding behavior, but also contractors'performance. By changing the size of public contracts, procurers can encourage (or discourage) market competition and improve contract performance, avoiding unnecessary cost overruns and project delays. In practice, there is no single solution about how to package public contracts. With procurement data from road projects in Nepal, this paper examines the optimal size of road contracts in rural areas. The optimum varies depending on policy objectives. To maximize the bidder participation, the length of road should be about 11 kilometers. To minimize cost overruns and delays, the contracts should be much larger at 17 and 21 kilometers, respectively. Compared with the current procurement practices, the findings suggest that procurers take more advantage of enlarging road packages, although contracts that are too large may increase the risk of discouraging firms from participating in public tenders.

Suggested Citation

  • Iimi, Atsushi & Benamghar, Radia, 2012. "Optimizing the size of public road contracts," Policy Research Working Paper Series 6028, The World Bank.
  • Handle: RePEc:wbk:wbrwps:6028
    as

    Download full text from publisher

    File URL: http://www-wds.worldbank.org/external/default/WDSContentServer/WDSP/IB/2012/04/05/000158349_20120405115155/Rendered/PDF/WPS6028.pdf
    Download Restriction: no
    ---><---

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Chong, Uven & Hopkins, Omar, 2016. "An international experience on the evolution of road costs during the project life cycle," Transport Policy, Elsevier, vol. 48(C), pages 60-66.

    More about this item

    Keywords

    Government Procurement; Transport Economics Policy&Planning; Debt Markets; Post Conflict Reconstruction; Contract Law;
    All these keywords.

    NEP fields

    This paper has been announced in the following NEP Reports:

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:wbk:wbrwps:6028. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    We have no bibliographic references for this item. You can help adding them by using this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Roula I. Yazigi (email available below). General contact details of provider: https://edirc.repec.org/data/dvewbus.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.