Abstract
A case study was performed on a Caltrans concrete rehabilitation project near Los Angeles on Interstate 10. The project was unique in that the contractor had to remove and replace 2.8 lane-km of concrete pavement in a 55-hour weekend closure. The existing cement treated base was not removed except in places where it had deteriorated, and a fast setting hydraulic cement concrete with a 4-hour opening strength was used for the surface concrete. The contractor used a concurrent working method in which demolition and concrete paving occurred simultaneously and only a single lane was removed and replaced. The contractor had only one standard width construction access lane (3.7 m) and a shoulder width of less than 3.0 m. The contractor successfully completed this 2.8 lane-km objective in 55 hours and was eligible for a $500,000 bonus per the contract. The demolition operation took 76 percent longer than planned, but it did not delay the overall progress of the project. The concrete paving activities, especially the concrete delivery and discharge, controlled the overall progress of the 55-hour weekend project. In terms of the number of slabs replaced per hour, the 55-hour weekend closure was 54 percent faster than the average nighttime closure conducted by the same contractor. The amount of the rehabilitation work performed over the 55-hour extended closure would have normally taken 2.5 weeks (16.4 days) of nighttime lane closures. If no work stoppages in the concrete paving had occurred, the maximum amount of rehabilitated road would have been 3.5 lane-km. In 10-hour nighttime closures, the contractor was able to remove and replace 50 slabs on average compared with 15 slabs for 7-hour nighttime closures. During weekend daylight hours, traffic through the construction zone was reduced by 30 to 60 percent compared with normal weekend traffic volume. During construction, the percentage of traffic diverting to other routes doubled over normal diversion in the daylight hours, but was only approximately 5 percent more than normal during the nighttime hours. The reduced traffic volumes passing the construction site indicated driver awareness of the weekend construction window and traffic lane closures. Caltrans did an excellent job of informing the public of the project through local media outlets (radio, newspapers, and television), signage, and brochures. The construction productivity data from the demolition and paving operation was used to validate a constructability and productivity analysis software coded by the University of California Berkeley (UCB). The average results from a deterministic and stochastic analysis were in agreement with the actual project productivity. The stochastic analysis showed that the expected range for the project productivity was between 2.2 and 3.4 lane-km for a 68-percent confidence interval with the average productivity being 2.8 lane-km.
Suggested Citation
Lee, E. B. & Roesler, J. R. & Harvey, J. T. & Ibbs, C. W., 2001.
"Case Study of Urban Concrete Pavement Reconstruction and Traffic Management for the I-10 (Pomona, CA) Project,"
Institute of Transportation Studies, Working Paper Series
qt6239f4rg, Institute of Transportation Studies, UC Davis.
Handle:
RePEc:cdl:itsdav:qt6239f4rg
Download full text from publisher
Citations
Citations are extracted by the
CitEc Project, subscribe to its
RSS feed for this item.
Cited by:
- Mateos, Angel & Harvey, John & Guada, Irwin & Wu, Rongzong & Lea, Jeremy & Nassiri, Somayeh, 2024.
"Twenty-Year Performance Review of Long-Life Jointed Plain Concrete Pavements,"
Institute of Transportation Studies, Working Paper Series
qt4jp5g461, Institute of Transportation Studies, UC Davis.
Most related items
These are the items that most often cite the same works as this one and are cited by the same works as this one.
- Mateos, Angel & Harvey, John & Guada, Irwin & Wu, Rongzong & Lea, Jeremy & Nassiri, Somayeh, 2024.
"Twenty-Year Performance Review of Long-Life Jointed Plain Concrete Pavements,"
Institute of Transportation Studies, Working Paper Series
qt4jp5g461, Institute of Transportation Studies, UC Davis.
Corrections
All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:cdl:itsdav:qt6239f4rg. See general information about how to correct material in RePEc.
If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.
If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .
If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.
For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Lisa Schiff (email available below). General contact details of provider: https://edirc.repec.org/data/itucdus.html .
Please note that corrections may take a couple of weeks to filter through
the various RePEc services.