Resource Constrained Project Scheduling Models under Random Disturbances

In: Perspectives in Modern Project Scheduling

Author

Listed:
  • Dimitri Golenko-Ginzburg

    (Academic College of Judea and Samaria
    Ben-Gurion University of the Negev)

  • Aharon Gonik

    (Sapir Academic College)

  • Anna Baron

    (Ben-Gurion University of the Negev)

Abstract

In the chapter we consider two different scheduling models for stochastic network projects. Models of the first type consider several simultaneously realized stochastic network projects of PERT type. Resource scheduling models of the second type also cover PERT type projects, but with two different kinds of renewable resources: 1 extremely costly resources (A-resources) which have to be obtained for a short time within the project’s time span. Such resources have to be prepared and delivered externally at planned moments, 2 renewable resources (B-resources) which are at the company’s disposal. In all types of models each projects’ activity utilizes several non-consumable related resources with fixed capacities, e.g. machines or manpower. For each operation, its duration is a random variable with given density function. The first problem centers on determining: the earliest starting moment for each project’s realization, the limited resource levels for each type of resources to be stored during the projects’ realization, the moments when resources are fed in and projects’ activities start, in order to minimize the average total expenses of hiring and maintaining resources subject to the chance constraints. For the second class of developed models the problem boils down: to predetermine in advance, i.e., before each project starts to be realized, a deterministic delivery schedule for A-resources which are not at the project’s disposal, to determine both the starting times and the resource capacities to be utilized for activities which require limited renewable B-resources which are at the project’s disposal, to determine the starting moment of each project’s realization, in order to minimize average total projects’ expenses subject to the chance constraint. Problems of resource project scheduling are solved via simulation, in combination with a cyclic coordinate descent method and a knapsack resource reallocation model.

Suggested Citation

  • Dimitri Golenko-Ginzburg & Aharon Gonik & Anna Baron, 2006. "Resource Constrained Project Scheduling Models under Random Disturbances," International Series in Operations Research & Management Science, in: Joanna Józefowska & Jan Weglarz (ed.), Perspectives in Modern Project Scheduling, chapter 0, pages 53-78, Springer.
  • Handle: RePEc:spr:isochp:978-0-387-33768-5_3
    DOI: 10.1007/978-0-387-33768-5_3
    as

    Download full text from publisher

    To our knowledge, this item is not available for download. To find whether it is available, there are three options:
    1. Check below whether another version of this item is available online.
    2. Check on the provider's web page whether it is in fact available.
    3. Perform a search for a similarly titled item that would be available.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:spr:isochp:978-0-387-33768-5_3. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    We have no bibliographic references for this item. You can help adding them by using this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Sonal Shukla or Springer Nature Abstracting and Indexing (email available below). General contact details of provider: http://www.springer.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.