Risk‐Informed Regulation and Safety Management of Nuclear Power Plants—On the Prevention of Severe Accidents

Author

Listed:
  • Risto Himanen
  • Ari Julin
  • Kalle Jänkälä
  • Jan‐Erik Holmberg
  • Reino Virolainen

Abstract

There are four operating nuclear power plant (NPP) units in Finland. The Teollisuuden Voima (TVO) power company has two 840 MWe BWR units supplied by Asea‐Atom at the Olkiluoto site. The Fortum corporation (formerly IVO) has two 500 MWe VVER 440/213 units at the Loviisa site. In addition, a 1600 MWe European Pressurized Water Reactor supplied by AREVA NP (formerly the Framatome ANP—Siemens AG Consortium) is under construction at the Olkiluoto site. Recently, the Finnish Parliament ratified the government Decision in Principle that the utilities' applications to build two new NPP units are in line with the total good of the society. The Finnish utilities, Fenno power company, and TVO company are in progress of qualifying the type of the new nuclear builds. In Finland, risk‐informed applications are formally integrated in the regulatory process of NPPs that are already in the early design phase and these are to run through the construction and operation phases all through the entire plant service time. A plant‐specific full‐scope probabilistic risk assessment (PRA) is required for each NPP. PRAs shall cover internal events, area events (fires, floods), and external events such as harsh weather conditions and seismic events in all operating modes. Special attention is devoted to the use of various risk‐informed PRA applications in the licensing of Olkiluoto 3 NPP.

Suggested Citation

  • Risto Himanen & Ari Julin & Kalle Jänkälä & Jan‐Erik Holmberg & Reino Virolainen, 2012. "Risk‐Informed Regulation and Safety Management of Nuclear Power Plants—On the Prevention of Severe Accidents," Risk Analysis, John Wiley & Sons, vol. 32(11), pages 1978-1993, November.
  • Handle: RePEc:wly:riskan:v:32:y:2012:i:11:p:1978-1993
    DOI: 10.1111/j.1539-6924.2012.01904.x
    as

    Download full text from publisher

    File URL: https://doi.org/10.1111/j.1539-6924.2012.01904.x
    Download Restriction: no

    File URL: https://libkey.io/10.1111/j.1539-6924.2012.01904.x?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Jylhä, Kirsti & Kämäräinen, Matti & Fortelius, Carl & Gregow, Hilppa & Helander, Juho & Hyvärinen, Otto & Johansson, Milla & Karppinen, Ari & Korpinen, Anniina & Kouznetsov, Rostislav & Kurzeneva, Eka, 2018. "Recent meteorological and marine studies to support nuclear power plant safety in Finland," Energy, Elsevier, vol. 165(PA), pages 1102-1118.
    2. Robert Goble & Vicki M. Bier, 2013. "Risk Assessment Can Be a Game‐Changing Information Technology—But Too Often It Isn't," Risk Analysis, John Wiley & Sons, vol. 33(11), pages 1942-1951, November.

    More about this item

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:wly:riskan:v:32:y:2012:i:11:p:1978-1993. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    We have no bibliographic references for this item. You can help adding them by using this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Wiley Content Delivery (email available below). General contact details of provider: https://doi.org/10.1111/(ISSN)1539-6924 .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.