Investigation of factors responsible for delays in the execution of adequately funded construction projects

Author

Listed:
  • Ogbeifun Edoghogho

    (University of Johannesburg, South Africa)

  • Pretorius Jan-Harm C

    (University of Johannesburg, South Africa)

Abstract

Many research efforts have identified funding as a critical factor responsible for the delays in the execution of construction projects. These funding challenges affect the client and contractors alike. However, there is limited information on why delays occur in sponsored projects with evidently adequate funding. Therefore, the study focuses on exploring the factors that impact the cash flow during the execution of sponsored construction projects. The multiple-site case-study method of qualitative research was adopted, involving five universities benefiting from the infrastructure funding provided by a government agency in Nigeria. The Delphi technique was used for data collection and analysis, complemented with interviews. The findings identified six factors causing the delays. They were divided into internal and external factors. The internal factors are faulty contractor selection processes resulting in delays by contractors and the failure to complete appropriate phases of a project. The external factors include the delays in the project management system of the funding agency in terms of inspection, monitoring, evaluation and progress certification. The research identified that the combined effect of internal and external factors negatively impacts the project cash flow, which in turn influences project delivery delays. Therefore, this study recommends improvements in the in-house contractor selection processes and the decentralisation of the project inspection, monitoring and evaluation operations of the funding agency. This will facilitate timely inspection, audit, and progress certification, enabling the early release of the second tranche of the project fund. This will ameliorate the negative effects arising due to low cash flow and associated delays in project delivery.

Suggested Citation

  • Ogbeifun Edoghogho & Pretorius Jan-Harm C, 2022. "Investigation of factors responsible for delays in the execution of adequately funded construction projects," Engineering Management in Production and Services, Sciendo, vol. 14(1), pages 93-102, March.
  • Handle: RePEc:vrs:ecoman:v:14:y:2022:i:1:p:93-102:n:10
    DOI: 10.2478/emj-2022-0008
    as

    Download full text from publisher

    File URL: https://doi.org/10.2478/emj-2022-0008
    Download Restriction: no

    File URL: https://libkey.io/10.2478/emj-2022-0008?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    References listed on IDEAS

    as
    1. Anna Zamojska & Joanna Próchniak, 2017. "Measuring the Social Impact of Infrastructure Projects: The Case of Gdańsk International Fair Co," Journal of Entrepreneurship, Management and Innovation, Fundacja Upowszechniająca Wiedzę i Naukę "Cognitione", vol. 14(4), pages 25-42.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Perz, Stephen G. & Mendoza, Elsa R.H. & dos Santos Pimentel, Alan, 2022. "Seeing the broader picture: Stakeholder contributions to understanding infrastructure impacts of the Interoceanic Highway in the southwestern Amazon," World Development, Elsevier, vol. 159(C).
    2. Mohamed M. Dhiaf & Khakan Najaf & Hazem Marashdeh & Osama F. Atayah & Guilherme F. Frederico, 2022. "The role of project’s initiatives focused on the reduction of environmental footprints during COVID-19: evidence from the United States firms," Operations Management Research, Springer, vol. 15(1), pages 413-427, June.
    3. Valentín-Sívico, Javier & Canfield, Casey & Low, Sarah A. & Gollnick, Christel, 2023. "Evaluating the impact of broadband access and internet use in a small underserved rural community," Telecommunications Policy, Elsevier, vol. 47(4).
    4. Danijela Toljaga-Nikolić & Marija Todorović & Marina Dobrota & Tijana Obradović & Vladimir Obradović, 2020. "Project Management and Sustainability: Playing Trick or Treat with the Planet," Sustainability, MDPI, vol. 12(20), pages 1-20, October.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:vrs:ecoman:v:14:y:2022:i:1:p:93-102:n:10. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Peter Golla (email available below). General contact details of provider: https://www.sciendo.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.