Comparison of cost and schedule performance of large public projects under P3 and traditional delivery models: a Canadian study

Author

Listed:
  • Jing Zhang
  • Fangjian Chen
  • X.-X. Yuan

Abstract

Cost overrun and schedule delay are pervasive in large public infrastructure projects in Canada and there is an ongoing debate over the root causes of these delivery risks and how best to mitigate them. Since public-private partnerships (P3s) have been long touted as an effective mitigating measure, this study aimed to provide comparative empirical evidence to explore this claim. By collecting cost and schedule data at three key milestones (decision to build, contract awarding and substantial completion) from 39 traditional projects and 27 P3 projects across Canada between 2004 and 2016, the study develops an innovative longitudinal profiling approach to inform the debate about the causes of cost overruns in large public projects. Statistical analyses of the collected data unambiguously demonstrate that P3s outperform non-P3 traditional delivery models during the construction stage in both cost overrun and schedule delay. However, substantial budget underestimation is found in the strategic decision-making process of both models of project delivery. Results from the study also provide solid objective grounds for the development of advanced value-for-money assessment methodology.

Suggested Citation

  • Jing Zhang & Fangjian Chen & X.-X. Yuan, 2020. "Comparison of cost and schedule performance of large public projects under P3 and traditional delivery models: a Canadian study," Construction Management and Economics, Taylor & Francis Journals, vol. 38(8), pages 739-755, August.
  • Handle: RePEc:taf:conmgt:v:38:y:2020:i:8:p:739-755
    DOI: 10.1080/01446193.2019.1645344
    as

    Download full text from publisher

    File URL: http://hdl.handle.net/10.1080/01446193.2019.1645344
    Download Restriction: Access to full text is restricted to subscribers.

    File URL: https://libkey.io/10.1080/01446193.2019.1645344?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Spohr, Jonas & Wikström, Kim & Ronikonmäki, Niko-Matti & Lepech, Michael & In, Soh Young, 2024. "Are private investors overcompensated in infrastructure projects?," Transport Policy, Elsevier, vol. 152(C), pages 1-8.
    2. Ceric Anita & Ivic Ivona, 2021. "Network analysis of interconnections between theoretical concepts associated with principal–agent theory concerning construction projects," Organization, Technology and Management in Construction, Sciendo, vol. 13(2), pages 2450-2464, January.
    3. Mateusz Trzeciak & Izabela Jonek-Kowalska, 2021. "Monitoring and Control in Program Management as Effectiveness Drivers in Polish Energy Sector. Diagnosis and Directions of Improvement," Energies, MDPI, vol. 14(15), pages 1-25, July.

    More about this item

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:taf:conmgt:v:38:y:2020:i:8:p:739-755. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    We have no bibliographic references for this item. You can help adding them by using this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Chris Longhurst (email available below). General contact details of provider: http://www.tandfonline.com/RCME20 .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.