How contractors price risk in bids: theory and practice

Author

Listed:
  • Samuel Laryea
  • Will Hughes

Abstract

Formal and analytical models that contractors can use to assess and price project risk at the tender stage have proliferated in recent years. However, they are rarely used in practice. Introducing more models would, therefore, not necessarily help. A better understanding is needed of how contractors arrive at a bid price in practice, and how, and in what circumstances, risk apportionment actually influences pricing levels. More than 60 proposed risk models for contractors that are published in journals were examined and classified. Then exploratory interviews with five UK contractors and documentary analyses on how contractors price work generally and risk specifically were carried out to help in comparing the propositions from the literature to what contractors actually do. No comprehensive literature on the real bidding processes used in practice was found, and there is no evidence that pricing is systematic. Hence, systematic risk and pricing models for contractors may have no justifiable basis. Contractors process their bids through certain tendering gateways. They acknowledge the risk that they should price. However, the final settlement depends on a set of complex, micro-economic factors. Hence, risk accountability may be smaller than its true cost to the contractor. Risk apportionment occurs at three stages of the whole bid-pricing process. However, analytical approaches tend not to incorporate this, although they could.

Suggested Citation

  • Samuel Laryea & Will Hughes, 2008. "How contractors price risk in bids: theory and practice," Construction Management and Economics, Taylor & Francis Journals, vol. 26(9), pages 911-924.
  • Handle: RePEc:taf:conmgt:v:26:y:2008:i:9:p:911-924
    DOI: 10.1080/01446190802317718
    as

    Download full text from publisher

    File URL: http://www.tandfonline.com/doi/abs/10.1080/01446190802317718
    Download Restriction: Access to full text is restricted to subscribers.

    File URL: https://libkey.io/10.1080/01446190802317718?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. João Adelino Ribeiro & Paulo Jorge Pereira & Elisio Moreira Brandão, 2020. "A real options approach to optimal bidding in construction projects considering volume uncertainty," Managerial and Decision Economics, John Wiley & Sons, Ltd., vol. 41(4), pages 631-640, June.
    2. Jin Woo Won & Wooyong Jung & Seung Heon Han & Sungmin Yun & Bonsang Koo, 2019. "What Enables a High-Risk Project to Yield High Return from a Construction Contractor’s Perspective?," Sustainability, MDPI, vol. 11(21), pages 1-17, October.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:taf:conmgt:v:26:y:2008:i:9:p:911-924. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    We have no bibliographic references for this item. You can help adding them by using this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Chris Longhurst (email available below). General contact details of provider: http://www.tandfonline.com/RCME20 .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.