Flow Shop Problems with Time Lags

Author

Listed:
  • Wlodzimierz Szwarc

    (University of Wisconsin, Milwaukee)

Abstract

This paper defines a model that covers the multimachine extensions of all existing flow-shop problems with time lags as well as flow-shop problems where setup, processing and release times are separated. Approximate solutions and lower completion time bounds are developed for the restricted and unrestricted cases.

Suggested Citation

  • Wlodzimierz Szwarc, 1983. "Flow Shop Problems with Time Lags," Management Science, INFORMS, vol. 29(4), pages 477-481, April.
  • Handle: RePEc:inm:ormnsc:v:29:y:1983:i:4:p:477-481
    DOI: 10.1287/mnsc.29.4.477
    as

    Download full text from publisher

    File URL: http://dx.doi.org/10.1287/mnsc.29.4.477
    Download Restriction: no

    File URL: https://libkey.io/10.1287/mnsc.29.4.477?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Suliman, S. M. A., 2000. "A two-phase heuristic approach to the permutation flow-shop scheduling problem," International Journal of Production Economics, Elsevier, vol. 64(1-3), pages 143-152, March.
    2. Riezebos, J. & Gaalman, G. J. C., 1998. "Time lag size in multiple operations flow shop scheduling heuristics," European Journal of Operational Research, Elsevier, vol. 105(1), pages 72-90, February.
    3. Yu, Tae-Sun & Han, Jun-Hee, 2021. "Scheduling proportionate flow shops with preventive machine maintenance," International Journal of Production Economics, Elsevier, vol. 231(C).
    4. Botta-Genoulaz, Valerie, 2000. "Hybrid flow shop scheduling with precedence constraints and time lags to minimize maximum lateness," International Journal of Production Economics, Elsevier, vol. 64(1-3), pages 101-111, March.
    5. Guinet, Alain & Legrand, Marie, 1998. "Reduction of job-shop problems to flow-shop problems with precedence constraints," European Journal of Operational Research, Elsevier, vol. 109(1), pages 96-110, August.
    6. Allahverdi, Ali & Gupta, Jatinder N. D. & Aldowaisan, Tariq, 1999. "A review of scheduling research involving setup considerations," Omega, Elsevier, vol. 27(2), pages 219-239, April.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:inm:ormnsc:v:29:y:1983:i:4:p:477-481. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    We have no bibliographic references for this item. You can help adding them by using this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Chris Asher (email available below). General contact details of provider: https://edirc.repec.org/data/inforea.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.