Abstract
Purpose. The purpose of this study is to examine the causes of delays in road construction projects in the Benin Republic from the consultant, client, and contractor perspectives. Design/Methodology/Approach. Through construction project reports, 20 factors that could cause delays in road construction projects were identified. The factors were arranged into a questionnaire, which was distributed to three separate experts. The fuzzy PIPRECIA (PIvot Pairwise RElative Criteria Relevance Assessment) method was used to calculate the independent importance of each delay factor. The Spearman and Pearson correlation coefficients were used to test the method’s consistency. Findings. The top five road construction project delays in the Benin Republic, according to the analysis of the 20 factors considered, are project funding, slowness during the client-endorsed payment process, scarcity of professional personnel, delay in indemnifying reimbursement (land-owners), and price escalation. This shows that of the various types of delays, the financial delay group is the most crucial. Originality/value. This study evaluates the causes of delays in road construction projects in the Benin Republic for the first time in literature. This study also examined the top 5 delay factors in road construction projects. This study is based on reports from road construction projects and a performed questionnaire survey. Based on the findings, measures have been formulated to aid project managers to alleviate the road construction delays in the Benin Republic. In addition, this study is practical for both scholars and road construction parties and provides a complete and verifiable analysis of the progress of a road construction project to make it easier and attain a competitive level of time, cost, and quality for successful road construction.
Suggested Citation
Željko Stević & Mouhamed Bayane Bouraima & Marko Subotić & Yanjun Qiu & Peter Antwi Buah & Kevin Maraka Ndiema & Christian Magloire Ndjegwes & Naeem Jan, 2022.
"Assessment of Causes of Delays in the Road Construction Projects in the Benin Republic Using Fuzzy PIPRECIA Method,"
Mathematical Problems in Engineering, Hindawi, vol. 2022, pages 1-18, April.
Handle:
RePEc:hin:jnlmpe:5323543
DOI: 10.1155/2022/5323543
Download full text from publisher
Corrections
All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:hin:jnlmpe:5323543. See general information about how to correct material in RePEc.
If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.
We have no bibliographic references for this item. You can help adding them by using this form .
If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.
For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Mohamed Abdelhakeem (email available below). General contact details of provider: https://www.hindawi.com .
Please note that corrections may take a couple of weeks to filter through
the various RePEc services.