Revolutionising the 4D BIM Process to Support Scheduling Requirements in Modular Construction

Author

Listed:
  • Mohammad Mayouf

    (Faculty of Computing Engineering and the Built Environment (CEBE), College of the Built Environment, Birmingham City University, Birmingham B5 5JU, UK
    Zigurat Global Institute of Technology, 08018 Barcelona, Spain)

  • Jamie Jones

    (Willmott Dixon Interiors, Birmingham B4 6GH, UK)

  • Faris Elghaish

    (School of Natural and Built Environment, Queen University Belfast, Belfast BT7 1NN, UK)

  • Hassan Emam

    (Zigurat Global Institute of Technology, 08018 Barcelona, Spain)

  • E. M. A. C. Ekanayake

    (Faculty of Computing Engineering and the Built Environment (CEBE), College of the Built Environment, Birmingham City University, Birmingham B5 5JU, UK)

  • Ilnaz Ashayeri

    (Faculty of Computing Engineering and the Built Environment (CEBE), College of the Built Environment, Birmingham City University, Birmingham B5 5JU, UK)

Abstract

Given the heightened importance of revolutionising 4D BIM-based construction scheduling in modular construction, it has become vital to explore how 4D-BIM could be integrated with the lean concept. Therefore, this research aims to develop a lean-integrated process model to revolutionise the 4D BIM-based construction scheduling in modular construction projects. A case study approach was used to obtain the data. The data was obtained using semi-structured interviews with construction scheduling professionals, site observations, and extracts from the BIM model used within the selected case in the UK. Findings showed that conventional (component/object based) 4D BIM supersedes conventional scheduling methods in terms of foreseeing potential implications during design and construction. The findings also showed that lean-integrated 4D BIM in modular construction have different considerations when compared with component/object-based scheduling. A lean-integrated 4D BIM process model was developed from the analysis and it was validated using an interactive workshop with eight participants from two UK construction companies and two modular construction manufacturers. The developed process model identified a number of considerations for 4D BIM in modular projects including constructability, operations, health and safety risks and time. This study suggested the further potential of 4D BIM in scheduling for modular construction projects.

Suggested Citation

  • Mohammad Mayouf & Jamie Jones & Faris Elghaish & Hassan Emam & E. M. A. C. Ekanayake & Ilnaz Ashayeri, 2024. "Revolutionising the 4D BIM Process to Support Scheduling Requirements in Modular Construction," Sustainability, MDPI, vol. 16(2), pages 1-17, January.
  • Handle: RePEc:gam:jsusta:v:16:y:2024:i:2:p:476-:d:1313561
    as

    Download full text from publisher

    File URL: https://www.mdpi.com/2071-1050/16/2/476/pdf
    Download Restriction: no

    File URL: https://www.mdpi.com/2071-1050/16/2/476/
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Pan Gong & Ningshuang Zeng & Kunhui Ye & Markus König, 2019. "An Empirical Study on the Acceptance of 4D BIM in EPC Projects in China," Sustainability, MDPI, vol. 11(5), pages 1-19, March.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Zezhou Wu & Mingyang Jiang & Yuzhu Cai & Hao Wang & Shenghan Li, 2019. "What Hinders the Development of Green Building? An Investigation of China," IJERPH, MDPI, vol. 16(17), pages 1-18, August.

    More about this item

    Keywords

    4D BIM; lean; scheduling; modular;
    All these keywords.

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:gam:jsusta:v:16:y:2024:i:2:p:476-:d:1313561. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: MDPI Indexing Manager (email available below). General contact details of provider: https://www.mdpi.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.