Timing Optimization Method for Pumped Storage Plant Construction Considering Capital Expenditure Capacity Feedback

Author

Listed:
  • Jie Jiao

    (State Grid Sichuan Economic Research Institute, Chengdu 610041, China)

  • Xiaoquan Lei

    (State Grid Power Company of Sichuan Province, Chengdu 610041, China)

  • Puyu He

    (State Grid Sichuan Economic Research Institute, Chengdu 610041, China)

  • Qian Wang

    (State Grid Sichuan Economic Research Institute, Chengdu 610041, China)

  • Guangxiu Yu

    (State Grid Sichuan Economic Research Institute, Chengdu 610041, China)

  • Wenshi Ren

    (State Grid Sichuan Economic Research Institute, Chengdu 610041, China)

  • Shaokang Qi

    (School of Economics and Management, North China Electric Power University, Beijing 102206, China)

Abstract

With the extensive integration of renewable energy into the power grid, pumped storage power plants have become an essential component in the development of modern power systems due to their rapid response capabilities, advanced technology, and other beneficial features. However, high construction costs and irrational capital expenditure and construction schedules have constrained the robust and sustainable growth of pumped storage plants. Therefore, this paper proposes a pumped storage plant construction timing optimization method considering capital expenditure capacity feedback. Initially, an analysis is conducted on the factors that influence the capital expenditure costs of pumped storage power plants throughout their lifecycle. Next, the value of investing in pumped storage plants is assessed across three different aspects: economics, environment, and reliability. Finally, according to the principle of dynamic planning combined with the actual needs and capital expenditure potential of pumped storage plants, the sum of the capital expenditure effectiveness values in each stage is used as the indicator function of each stage to construct the pumped storage plants project capital expenditure timing optimization model, and a simulation analysis is carried out with Province Z as an example to verify the validity and applicability of the proposed model. The findings indicate that the suggested model is effective in balancing the implementation time of individual projects to achieve the maximum cumulative capital expenditure performance over the entire planning period.

Suggested Citation

  • Jie Jiao & Xiaoquan Lei & Puyu He & Qian Wang & Guangxiu Yu & Wenshi Ren & Shaokang Qi, 2024. "Timing Optimization Method for Pumped Storage Plant Construction Considering Capital Expenditure Capacity Feedback," Energies, MDPI, vol. 18(1), pages 1-20, December.
  • Handle: RePEc:gam:jeners:v:18:y:2024:i:1:p:47-:d:1554195
    as

    Download full text from publisher

    File URL: https://www.mdpi.com/1996-1073/18/1/47/pdf
    Download Restriction: no

    File URL: https://www.mdpi.com/1996-1073/18/1/47/
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Putra, Lingga Aksara & Köstler, Marlit & Grundwürmer, Melissa & Li, Liuyi & Huber, Bernhard & Gaderer, Matthias, 2025. "State estimation of a biogas plant based on spectral analysis using a combination of machine learning and metaheuristic algorithms," Applied Energy, Elsevier, vol. 377(PA).
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.

      Corrections

      All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:gam:jeners:v:18:y:2024:i:1:p:47-:d:1554195. See general information about how to correct material in RePEc.

      If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

      If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

      If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

      For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: MDPI Indexing Manager (email available below). General contact details of provider: https://www.mdpi.com .

      Please note that corrections may take a couple of weeks to filter through the various RePEc services.

      IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.